Auto Bracket Shop: VMCs with Robot Tending

An East China auto supplier ran four VMC-850 machines and two IR-20 cells, cutting bracket takt from 86 s to 62 s.

p1

The plant feeds brackets to an OEM on two shifts. Six operators loaded machines; changeover was tribal knowledge. Parts weigh about 3.2 kg; the new takt target was under 65 s.

We split roughing, drilling and tapping across four VMC-850 machines. Two IR-20 cells share a magazine. One fence door was rotated to keep the aisle.

After two weeks of debug, takt held at 62 s and changeover fell from 40 minutes to about 18. Crates shipped from Guangzhou with the customer’s marks.

Frequently Asked Questions

View all →

We issue invoice, packing list, contract and technical data. Certificate of origin, inspection or embassy legalization is extra by country. Tell us any HS-code preference so the goods description matches your license.

Standard VMC-850 and AP-400 builds take about 25–40 days. Conveyors follow meter count; robot cells follow gripper complexity. Rush jobs are answered after we check castings and electrical stock—no empty “next week” promises.

Machines ship in export wooden or steel-frame crates with moisture and rust protection. Marks, port and fumigation follow your forwarder. Precision parts are boxed separately with a packing list for arrival checks.

Get Free Quote